08: Why Most Renovations Fail in the Planning Stage — How to Master Project Management

The Remodel Timeline Most Homeowners Get Wrong

(And How to Avoid Costly Scheduling Mistakes)

If you’ve ever wondered,
“What actually happens after the design is done?”
you are not alone.

This is one of the most common questions I get from homeowners heading into construction — and honestly, it’s a fair one.

Renovations involve a lot of moving parts. Multiple trades. Tight timelines. And if things happen out of order?
💥 Delays
💥 Extra costs
💥 Contractors showing up and leaving because they can’t work yet

I know this because I learned the hard way.

My Early (Very Humbling) Lesson in Order of Operations

When I first started managing construction projects, I didn’t know what I didn’t know.

I brought contractors in too early.
They’d walk the space and say things like:

  • “I can’t do this yet.”

  • “That needs to be done first.”

  • “This is in my way.”

And there I was — feeling totally unprepared.

I once tried to schedule appliance installation four separate times before realizing why it kept failing. 🙃

That’s why I recorded this episode — to save you from learning this lesson the hard way.

First, Let Me Be Very Clear About One Thing

🚨 Demo is NOT the first step of a remodel. 🚨

You’ll hear me say this over and over:

Design before demo. Always.

Before construction ever starts, you should already have:

  • A completed design

  • A clear budget

  • Your selections made

  • A plan

Everything below assumes you’ve already done that work and are officially entering the construction phase.

Need Help With Your Remodel?

Book Your 1 hour Design Consultation

Your Customized Plan So You Can Renovate With Clarity and Confidence

Let me show you!

Step-by-Step (Without the Overwhelm)

🧱 1. Demo

  • Fast and dramatic.

  • Everything gets ripped out so you can rebuild.

Remember: demo only happens after planning is done.

🔨 2. Framing

This can be big or small:

  • Moving walls

  • Adding niches

  • Pony walls

  • Extending walls for cabinetry

Framing must happen before plumbing and electrical so everything has a structure to run through.

🚿 3. Plumbing Rough-In

This is all the inside-the-wall work:

  • Valves

  • Water lines

  • Drain locations

Plumbers come twice:

  • Rough-in (now)

  • Finish install (later)

💡 4. Electrical Rough-In

Electricians handle:

  • New or moved outlets

  • Lighting locations

  • Appliance wiring

  • Island power

At this stage, you’ll see boxes and wires — not finished outlets yet.

🌬️ 5. HVAC Rough-In

Common examples:

  • Hood venting

  • Bath fans

  • Duct changes

This is where surprises often pop up once walls are open.

✅ 6. Inspections

Before you close walls:

  • Plumbing

  • Electrical

  • HVAC

⚠️ Never drywall before passing inspections.

.

🧱 7. Drywall

Walls get closed back up.
This happens after all rough-ins are approved.

Where the Order Can Flex a Bit

From here on, things can move depending on:

  • Contractor preferences

  • Flooring type

  • Project scope

But the logic still matters.

🪚 8. Cabinetry Install

I typically install cabinets:

  • After drywall

  • Before flooring

  • Before painting

This allows:

  • Accurate countertop templating

  • Efficient scheduling

🪨 9. Countertop Templating (Then Waiting)

Once cabinets are in:

  • Fabricators measure

  • Counters get made

⏳ This creates a natural waiting period — perfect for…

LISTEN ON APPLE PODCAST

LISTEN ON SPOTIFY

🪵 10. Flooring

Flooring often fills this gap:

  • Saves time

  • Keeps the project moving

Whether floors go under cabinets depends on:

  • Material type

  • Budget

  • Design preference

🪨 11. Countertop Install

Once counters are in, a lot can finally move forward.

🧱 12. Tile Work

Tile installers need:

  • Cabinets in

  • Countertops installed

Backsplashes and showers happen here.

🎨 13. Painting

I usually paint after:

  • Tile

  • Flooring

  • Cabinets

✔️ Everything gets protected
✔️ Touch-ups are easier
✔️ Cleaner final result

🚰 14. Finish Plumbing & Electrical

Now the “pretty stuff” goes in:

  • Faucets

  • Shower heads

  • Pendants

  • Outlet covers

This is when spaces start to feel finished.

🍳 15. Appliance Install

Appliances come near the very end — for good reason.

They need:

  • Power

  • Water

  • Finished connections

This is where I went wrong early in my career 😅

🧰 16. Cabinet Finish Work

Cabinet teams return to:

  • Adjust doors & drawers

  • Install hardware

  • Add toe kicks

  • Touch up paint

🪛 17. Final Touch-Ups

All the little things:

  • Accessories

  • Trim

  • Minor fixes

  • Paint touch-ups

If it’s not in someone’s scope… it becomes your job.

✅ 18. Final Inspections

Inspectors return to confirm:

  • Everything is connected

  • Everything functions

  • Code is met

Only then is the project truly complete.

Need Help With Your Remodel?

Book Your 1 hour Design Consultation

Your Customized Plan So You Can Renovate With Clarity and Confidence

Let me show you!

The Big Takeaway

You don’t need to memorize every step.

What you do need is:

  • A basic roadmap

  • An understanding of why order matters

  • Confidence to ask trades:
    “What needs to be done before you arrive?”

🎧 This episode of Preparing for Your Home Remodel walks through this timeline in real-time so you can plan ahead — before construction chaos begins.